登陆注册
20556800000005

第5章

UNIQUE ASPECTS OF GOVERNMENT CONTRACTS

Many of the rules that apply to contracts in general—contracts that businesspeople make all the time—apply to government contracts. But carrying out a government contract can be very different from carrying out the typical commercial contract. This chapter explores several of the unique aspects of administering government contracts.

With the government, a deal is a deal as described in the contract—

1. Unless the government intentionally and unilaterally changes it using the "Changes" clause

2. Unless the government inadvertently changes it through a constructive change

3. Although the deadlines in the contract are not really deadlines, just suggestions

4. Although clauses left out are in there anyway

5. Although the government can end the deal prematurely without paying breach of contract damages.

THE GOVERNMENT INTENTIONALLY AND UNILATERALLY CHANGES THE CONTRACT USING THE CHANGES CLAUSE

The Changes clause in government contracts is unique. In the business world, a deal is a deal. If you want to change the deal, you can—but only if the other party agrees. In government contracting, however, a deal is a deal unless it is changed by the government using the Changes clause, with or without the contractor's consent.

The heart of the Changes clause, FAR 52.243-1, is section (a):

Changes—Fixed Price (Aug 1987)

(a) The Contracting officer may, at any time, without notice to the sureties, if any, make changes within the general scope of this contract in any one or more of the following:

(1) Drawings, designs, or specifications …;

(2) Method of shipment or packing;

(3) Place of delivery.

The Changes clause is a very important clause. It allows the government to respond quickly to changing needs, such as changes in congressional or agency priorities. If the contractor doesn't want to make the change, the government can force the contractor to make it.

But everything has its limits, and that includes the Changes clause. The government cannot use it to change everything in the contract. The clause itself has two self-imposed limits: the change must be "within the scope of the contract," and only those parts of the contract listed in the clause (like drawings, designs, or specifications) may be changed.

Manager Alert

With limited exceptions, if the contractor doesn't want to make the change, the government can force the contractor to make it.

Within the Scope of the Contract

With such a handy clause like the Changes clause, there's sure to be mischief. One example is what is called a "cardinal change." The dictionary defines cardinal as "principal," "fundamental," and "chief." Courts and the Government Accountability Office (GAO) don't look on cardinal changes very kindly. They see the Changes clause as a device that could be used to make an end run around full and open competition by adding work that should be competed to an existing contract. So the test of when a change is an improper cardinal change—and "beyond the scope" of the contract—focuses on the change's effect on competition. The government may not modify a contract to the extent that it is materially different from the original contract. In other words, does the original contract as modified require essentially the same performance? If so, the additional work need not be competed.

One court used this definition:

A cardinal change … occurs when the government effects an alteration in the work so drastic that it effectively requires the contractor to perform duties materially different from those originally bargained for.[1]

Here's how GAO describes its test:

In assessing whether the modified work is essentially the same as the effort for which the competition was held and for which the parties contracted, we consider factors such as the magnitude of the change in relation to the overall effort, including the extent of any changes in the type of work, performance period, and costs between the modification and the underlying contract.[2]

A broader scope of work to start with (in the original contract) allows a broader change in that scope. If an agency uses the Changes clause to get "more" under a procurement, vendors might see its use of the clause as an end run around full and open competition. The vendors might believe that the "more" should have been competed among all vendors instead of obtained from the incumbent vendor. But if an agency has given vendors the chance to bid on a contract that has a broad scope, the losing vendors can't fairly complain when the broad scope is used to get—through a modification to the contract—something the losing offerors think should be a separate procurement.

One case provides a good example. For years, H.G. Properties (HGP) housed the National Park Service's Western Archeological and Conservation Center (WACC). WACC has about five million museum objects and gives advice on archeology to parks in the western United States. As the contract with HGP was about to end, the Park Service issued a solicitation for, in its terms, a "Cadillac" or state-of-the-art facility for WACC. When the awarded contract was modified, a competitor protested the change as beyond scope. The CAFC disagreed. The broad scope of the original solicitation let the Park Service make a broad modification. The original solicitation "encouraged bidders to submit suggested modifications to the solicitation so as to create a state of the art facility. Accordingly, the 'scope' of the contract would be understood to embrace changes or modifications to these requirements."[3]

Indicators of Beyond-Scope Work

One indicator of a beyond-scope change is a change in the type of work. But, as one GAO decision shows, garbage collection is still garbage collection, even if it is changed to be done with contractor-owned rather than government-owned equipment.

Mark Dunning Industries had a contract to collect and dispose of garbage at Fort Rucker, Alabama. The contract was comprehensive, covering the waterfront of garbage collection. Dunning was to pick up residential, commercial, industrial, and community area garbage. One of the contract tasks let Dunning use front-loading government vehicles to collect the garbage. But the front-loading government vehicles weren't very reliable, so the Army changed the contract to have Dunning provide these trucks as part of the contract. The price of the contract was increased about 20 percent. GAO found the change to be within scope.

GAO emphasized that "[t]he Army's modification did not make any changes to the original nature and purpose of the contract. First, the front-loading refuse collection service is but one of the multiple refuse collection services [that were] to be performed under the contract, the bulk of which were to be performed using the contractor's trucks. Moreover, the contract specifically included as one of the multiple line items the requirement that the contractor would perform the very front loading refuse collection services that were the subject of this modification, albeit with government-furnished vehicles." In addition, GAO noted that the change was made because the government's equipment was broken. "Since the essence of the requirement was for the contractor to provide front loading refuse collection, the Army's modification, merely shifting the responsibility for the vehicles and the containers needed to carry out the services to the contractor, did not substantially change the contract, nor make it essentially different."[4]

Large cost increases are also a factor to be considered, but costs, curiously, are not a surefire indicator of a beyond-scope change.

Manager Alert

Costs are not a surefire indicator of a beyond-scope change.

In one case, increasing the contract amount by 80 percent was considered a beyond-scope change.

The government wanted to have a "flexible" contract for custodial services. The winning offeror would give the government an "Add/delete of Service Cost Sheet" right after winning the contract. The sheet would list the winning contractor's prices to be used in negotiating with the Air Force for adding or deleting services after award. The government expected the additions or deletions to be minimal. Once the contract was awarded, however, the winning contractor's cost sheet itself was deleted, making service changes negotiable one-by-one and at much higher costs.

The court acknowledged that whether the contract is "materially different" could be measured by the difference in costs between the contract as awarded and as modified. But the amount of increase alone isn't the only factor. The change in costs must be put in the context of what the original bidders thought they were getting into if they won the contract. A 100 percent increase in funding, under the circumstances, was not considered a cardinal change in one precedent. In that case, the government had estimated the number of hours the eventual winner of a security services contract would have to provide. Because the number of hours in the contract that all the bidders had fought for was simply an estimate, there had been no "beyond scope" change when the actual number of hours under that contract was increased to double the original amount due to an emergency. But here, there had been no such change in circumstances and the contract price had increased by 80 percent. The change therefore was beyond scope.[5]

Modifications of a contract that reduce the scope of the contract might also be beyond scope and have to be competed.

A contract called for providing and recycling but not disposing of something. The government modified the contract to require providing and recycling or disposing of something. The "disposing" was not only a much cheaper task, but "disposing" also had more competitors waiting in the wings to do the work if the agency would compete the work as modified. GAO held that the reduction was beyond the scope of the original contract, so the modification should have been competed. "Here, the RFP did not anticipate that the contractor could be relieved of the recycling requirement or that a disposal effort could be ordered in lieu of recycling. Furthermore … the costs of leasing plastic media with no recycling requirements is as much as 50 percent less…." Also, there were at least four competitors who could do the work.[6]

One significant change in the government's one-sided ability to change the deal is in FAR 52.212-4, Commercial Items Contract Terms and Conditions. According to clause (c), Changes, any change in the terms and conditions of the commercial items contract must be mutually agreed upon.

THE GOVERNMENT INADVERTENTLY CHANGES THE DEAL THROUGH A CONSTRUCTIVE CHANGE

The money a contractor gets under a government contract may usually be increased only if the government voluntarily issues a modification of the contract, usually under the contract's Changes clause.

One classic exception to this rule is a constructive change. When there is a constructive change, judges in effect become government contracting officers. As contracting officers, the judges find that although the government did not expressly change the contract, something the government made the contractor do changed the contract, and therefore the contractor should get paid for the change. Judges, of course, do not have warrants, so a judge cannot order a formal change. But judges can construe things any way they want to. In these instances, what the government did is construed by the judge as a change to the contract, hence the phrase constructive change.

Because constructive changes are so important and so common, we need a good definition:

A constructive change occurs where a contractor performs work beyond the contract requirements, without a formal order under the Changes clause, either due to an informal order from, or through the fault of, the government. Before the contractor can recover, it must show that the government ordered it to perform the additional work. The contractor cannot merely show that the government disapproved a mode of performance. Rather, the contractor must show that the government actually compelled the additional work. The government order need not be formal or in writing. The additional work must be beyond the requirements of the pertinent specifications or drawings. At the same time, the additional work performed by the contractor cannot be beyond the general scope of the contract. Drastic modifications or fundamental alterations ordered by the government beyond the scope of the contract will constitute a breach of contract. The additional work must therefore be beyond the requirements of the contract, albeit still within the general scope of the contract.[7]

When a constructive change happens, the government typically does not think the contract is changed. For example, when asked by a contractor to interpret words in a contract, the government tries to interpret the contract correctly; the government thinks it is simply interpreting the contract. But if a contractor disagrees, files a claim, and convinces the judge that the contractor's interpretation is the correct one, the government will learn—years later—that its interpretation was wrong and had changed the contract. So in a sense, the government does not issue a constructive change; only a judge issues a constructive change.

There should be no stigma attached to a constructive change to a contract. The government was administering the contract as it believed to be fair, but a judge disagreed and the judge had the last word.

A constructive change can sneak up on the government and can appear in all sorts of disguises. The most common types are extras.

Generally, "extras" are candidates for a constructive change. Judges don't like the government getting something for nothing. So when the government makes the contractor do more expensive work but refuses to pay for it, a judge can bring out the constructive change theory to make the government pay for the extras.

Manager Alert

Not only a contracting officer can make a constructive change; so can other government employees, like government managers.

For example the U.S. Postal Service (USPS) issued a solicitation calling for trucks to carry mail long distances. But the solicitation seemed to conflict with federal regulations by saying that drivers could work 12 straight hours; federal regulations said that drivers could work only 10 straight hours. One company, L.P. Fleming, Jr., Inc., noticed the difference but thought nothing of it since all USPS solicitations it had seen included that same language. Moreover, when the head of the company described how he intended to do the work—using only one driver—to a USPS contract specialist, that contract specialist never voiced any opposition to Fleming's plan and, in fact, recommended that Fleming get the contract.

During the course of the contract, federal regulations changed. As applied to Fleming's work, they clearly made him use two drivers. After ignoring the earlier federal regulations, USPS now enforced the changed regulations, making Fleming spend money for two drivers. When USPS refused to increase Fleming's contract to pay for two drivers, Fleming went to the Postal Service Board of Contract Appeals. The board found that Fleming's interpretation of the contract—that one driver was okay—was reasonable and in fact "was shared by the government at the time of award and thereafter. Under these circumstances, that interpretation of the contract language governs. Therefore, when the contracting officer directed Fleming to perform the contract in accordance with the revised federal regulations, that direction had the effect of changing the contract provisions governing the allowable driving time…." The board concluded by making USPS pay for the extra work.[8]

The board came to this conclusion after addressing two important points in contract interpretation—reasonableness and reliance. Fleming's contract interpretation was reasonable: "Its drivers were regularly able to complete the trips" under the solicitation's time limits. And Fleming's interpretation was also the one he had relied on in bidding the contract.

No discussion of a constructive change is complete without stressing that government employees other than the contracting officer can end up making a constructive change to a contract. This is true regardless of what the contract's clauses say. Government managers must therefore be careful to not make these constructive changes.

Any government employee can make a constructive change. For example, a government inspector looked at a newly installed roof that would let ponding water evaporate in 48 hours, the industry standard. But that was not good enough for him. He made the contractor change the roof to make water evaporate in 24 hours. A board of contract appeals made the government pay for the contractor's extra work. "Inspectors with authority to accept or reject work have been held to bind the government when they improperly reject the work. An extremely rigid, unreasonable, and arbitrary course of conduct by a government quality assurance representative constitutes an improper disruption of a contractor's performance that can work a constructive change entitling the contractor to an equitable adjustment under the changes clause." The contract contemplated that there would be some ponding. "Where there are no contract provisions establishing acceptance criteria, the standard used to pass on contract work is a standard customary within the industry. The rejection of the contractor's work … was unjustified."[9]

In this case, the inspector cost the government money even though the contract clauses seemed to prohibit that result. The contract said that "no understanding or agreement between the contractor and any Government employee other than the contracting officer would be effective or binding upon the Government." The board fit its decision into the terms of the standard clause. The inspector "was acting with the authority of the contracting officer in performing his inspection duties to obtain compliance with his interpretation of contract requirements."[10]

DEADLINES ARE NOT REALLY DEADLINES

Rule Number One: Read the contract. Rule Number Two: Don't believe everything you read in the contract. These rules pretty well sum up the way courts and boards see deadlines in FAR clauses—as merely suggestions.

For example, several clauses, including the heavily used Changes clause, say that a contractor "must" do something in 30 days. For example, the changes clause for fixed-price contracts, FAR 52.243-1, has a 30-day "deadline":

The Contractor must assert its right to an adjustment under this clause within 30 days from the date of receipt of the written order. However, if the Contracting officer decides that the facts justify it, the Contracting officer may receive and act upon a proposal submitted before final payment of the contract.

The Changes clause at FAR 52.243-4 has two deadlines: a 20-day deadline and a 30-day deadline:

(d) … no [equitable] adjustment … shall be made for any costs incurred more than 20 days before the Contractor gives written notice as required.

(e) The Contractor must assert its right to an adjustment under this clause within 30 days….

But the deadlines in these clauses are not faithfully and literally applied by courts and boards.

One reason is that these deadlines are not like a statute of limitations designed to end a contractor's right to do something. They are more like a warning, forcing the contractor to tell the government something—for example, that the contractor thinks the government has made a constructive change to its contract. If a contractor intends to get an equitable adjustment for the constructive change, the government has to know why the contractor thinks the government made a constructive change. So a deadline in a FAR clause helps force the contractor to give the government notice.

But if the government already knows about it, why demand that the deadline in the clause be slavishly observed? If the clause is designed to make sure the government knows something, and the government in fact already knows it (even without the contractor's giving the government notice), why allow lack of formal notice to defeat any right the contractor might have to an equitable adjustment?

In the classic decision that used this relaxed approach, the court gave this "wholesome" explanation:

To adopt [a] severe and narrow application of the notice requirements … would be out of tune with the language and purpose of the notice provisions, as well as with this court's wholesome concern that notice provisions in contract-adjustment clauses not be applied too technically and illiberally where the government is quite aware of the operative facts.[11]

What, then, are the rules on deadlines?

First, the rules shift the focus from "strictly following the deadlines" to "what harm has the government suffered because the contractor did not follow the deadlines"? In legalese, the issue is "prejudice." It's a "so what?" It's a contractor saying, in effect, "I was late, but so what? What was the harm to the government because I was late?"

Second, if the government wants to make a deadline a requirement and not a suggestion, it must tell the contractor what happens if the deadline is not met. Warning a contractor of the consequences of not following a deadline makes the time limit a real deadline.

Manager Alert

Warning a contractor of the consequences of not following a deadline makes the time limit a real deadline.

In one case, the court required strict compliance with the termination for convenience settlement proposal deadline. The clause said that if the proposal was not submitted within one year from the effective date of termination, the contracting officer could unilaterally determine the amount due and the contractor would lose the right to appeal the determination.[12]

In addition, a General Services Administration (GSA) clause requires a government lessor to apply for reimbursement of a tax increase within 60 days after paying the tax. The clause warns lessors that if the 60-day limit is not met, the lessor loses its right to reimbursement. The General Services Board of Contract Appeals has ruled that the 60-day deadline must be strictly observed.[13]

CLAUSES LEFT OUT ARE IN A GOVERNMENT CONTRACT ANYWAY

The Christian Doctrine, named after a 1963 decision of the Court of Federal Claims, holds that a mandatory clause inadvertently omitted from a government contract is in the contract nonetheless. Not all courts use the doctrine. The U.S. Court of Appeals for the District of Columbia Circuit has said, "Our court has never adopted the Federal Circuit's Christian doctrine."[14]

The CAFC gave a nice summary of what the Christian Doctrine covers and what it does not.

… the Christian Doctrine applies to mandatory contract clauses which express a significant or deeply ingrained strand of public procurement policy: a clause requiring plaintiff to exhaust administrative remedies before bringing suit for breach of lease; a clause promoting uniform treatment of "major issues" such as cost and pricing data when more than one military department is purchasing an item; a clause outlining proper pre-award negotiation procedures; and a clause implementing requirements of the Buy American Act…. However, the Christian Doctrine has also been employed to incorporate less fundamental or significant mandatory procurement contract clauses if not written to benefit or protect the party seeking incorporation … [like] a missing "Mistake in Bids" clause required under [the regulations to] be incorporated into the contract as requested by the government because the clause was written for the protection of contract bidders." [Internal citations and punctuation omitted.][15]

Examples of clauses incorporated into a contract under the Christian Doctrine include the following:

? Disputes concerning labor standards clause[16]

? Disputes clause[17]

? Assignment of claims clause[18]

? Default clause[19]

? Fair Labor Standards Act and Service Contract Act price adjustment clause[20]

? Changes clause[21]

? A small business set-aside clause making the small business contractor do at least 50 percent of the work[22]

? Service Contract Act provisions clause[23]

? Payments clause[24]

? Government-furnished property clause[25]

? Protest after award clause.[26]

THE GOVERNMENT PREMATURELY ENDS THE AGREEMENT

A deal is a deal—unless you are the government and have a "termination for convenience" clause as part of the deal. When you and I sign a contract, we don't have the luxury of deciding, unilaterally and on the cheap, that we don't want to carry out the contract any longer. If one of us wants to get out of the deal, we become liable for breach of contract damages. These damages include all the profit the other party would have made if we had stuck to our deal, so-called "anticipatory profits."

The government is different. It has the clout to set new rules for the deal—rules more favorable to itself.

This is not unfair. If somebody wants to contract with the federal government, the contractor knows going into the deal that the government might end the contract before the contractor has had the chance to make all the profit the contractor expected. Moreover, it's not as if the government's termination for convenience will do any real harm to the contractor. The government will pay the contractor all costs to date and the profit on that work. In addition, the government will pay the contractor's lawyers and accountants as they determine what those costs are. But, unlike we would, the government will not have to pay anticipatory profits as damages.

The heart of the clause is FAR 52.249-2(a):

Termination for Convenience of the Government (Fixed-Price) (APR2012)

(a) The Government may terminate performance of work under this contract in whole or, from time to time, in part if the Contracting officer determines that a termination is in the Government's interest. The Contracting officer shall terminate by delivering to the Contractor a Notice of Termination specifying the extent of termination and the effective date.

The critical issue here is, what is "the convenience of the government"? How far can the government push convenience? The answer is that the government can push convenience really far. An improper termination for convenience is rare.

That seems surprising. What is the convenience of the government? Although the courts and boards have been vigilant to guard against gross abuses, "[i]t is not the province of the courts to decide de novo whether termination was the best course. In the absence of bad faith or clear abuse of discretion the contracting officer's election to terminate is conclusive."[27]

Contractors will have a really hard time trying to prove the government's bad faith in a termination for convenience:

The contractor's burden to prove the Government acted in bad faith, however, is very weighty…. Any analysis of a question of Governmental bad faith must begin with the presumption that public officials act conscientiously in the discharge of their duties…. Due to this heavy burden of proof, contractors have rarely succeeded in demonstrating the Government's bad faith.[28]

It's in only a rare case that the government terminates a contract for convenience in bad faith.

Here's one:

Although wartime situations no longer limit use of the practice, the Government's authority to invoke a termination for convenience has, nonetheless, retained limits. The contracting officer may not terminate for convenience in bad faith, for example, simply to acquire a better bargain from another source…."[29]

Manager Alert

The contracting officer may not terminate a contract for convenience simply to get a better deal from another source.

It is also hard to prove that the government abused its discretion in terminating for convenience. Decisions show two common situations that are not an abuse of discretion: a termination for convenience after discovery of a cardinal change and a termination for convenience to further full and open competition.

A cardinal change is a significant change to the work under a contract. It's so significant that if the changed work were to be competitively bid, more or different bidders would try to get the contract. If the government discovers after the contract has been awarded that the work is significantly different from what it expected—a cardinal change—the government can terminate the contract for convenience and resolicit the work with a solicitation that accurately reflects the government's new understanding of the work.

In one case, a government contract anticipated that approximately 10 percent of the work would be asbestos removal. It turned out, however, that the asbestos removal work would be about 50 percent of the contract. Believing that this large increase in work constituted a cardinal change, the contracting officer terminated the contract for convenience and resolicited the work. The terminated contractor argued that the termination for convenience was an abuse of discretion, but the court disagreed: Under the circumstances, the contracting officer had ample justification for conducting a reprocurement competitively under the Competition in Contracting Act. "With this change in the scope of contract work, different bidders, like asbestos removal firms, may have entered the competition on the contract."[30]

NOTES

[1]AT&T Comunications Inc. v. Wiltel, 1 F.3d 1201, 1205 (Fed. Cir. 1993) (quoting Allied Materials & Equip. Co. v. United States, 215 Ct. Cl. 406, 409, 569 F.2d 562, 563-64 (1978)).

[2]Poly-Pacific Technologies, Inc., B-296029, June 1, 2005, 2005 CPD ? 105.

[3]HG Properties A, L.P. v. The United States & Quality Leasing & Development, 68 Fed. Appx. 192 (Fed. Cir. 2003).

[4]Atlantic Coast Contracting Inc., B-288969.4, June 21, 2002, 2002 CPD ? 104.

[5]Cardinal Maintenance Services, Inc., v. The United States. 63 Fed.Cl. 98 (2004).

[6]Poly-Pacific Technologies, Inc., supra.

[7]NavCom Defense Electronics, Inc. v. England, 53 Fed. Appx. 897 (Fed. Cir. 2002).

[8]J.P. Fleming, Inc., PSBCA No. 5197, February 3, 2006.

[9]A & D Fire Protection, Inc., ASBCA No. 53,103, 02-2 BCA ? 32053.

[10]Id.

[11]Hoel-Steffen Construction Co., v. United States, 456 F. 2d 760 (Ct. Cl. 1972).

[12]Do-Well Machine Shop, Inc. v. United States, 870 F.2d 637 (Fed. Cir. 1989).

[13]4J2R1C LP v. General Services Administration, GSBCA No. 15584, 02-1 BCA ? 31742.

[14]Amfac Resorts, L.L.C. v. U.S. Dept. of the Interior, 282 F.3d 818, 824, 350 U.S.App.D.C. ? 191, 197 (D.C. Cir. 2002) reversed on other grounds, National Park Hospitality Ass'n v. Department of Interior, 538 U.S. 803, 123 S.Ct. 2026, (2003).

[15]General Engineering & Mach. Works v. O'Keefe, 991 F.2d 775, 779-780 (Fed. Cir. 1993).

[16]M.E. McGeary Co., ASBCA No. 36788, 90-1 BCA ? 22512.

[17]Fireman's Fund Insurance Co., ASBCA No. 38284, 91-1 BCA ? 23439.

[18]Rodgers Construction, Inc., IBCA No. 2777, 92-1 BCA ? 24503.

[19]OFEGRO, HUDBCA No. 88-3410-C7, 91-3 BCA ? 24206; and H&R Machinists Co., ASBCA No. 38440, 91-1 BCA ? 23373.

[20]Telesec Library Services, ASBCA No. 42968, 92-1 BCA ? 24650; and Ace Services, Inc. v. General Services Administration, GSBCA No. 11331, 92-2 BCA ? 24943.

[21]GAI Consultants, Inc., ENGBCA No. 6030, 95-2 BCA ? 27620.

[22]Unit Data Service Corp. v. Department of Veterans Affairs, GSBCA No. 10775-P-R, 93-3 ? BCA ? 25964.

[23]Miller's Moving Co., ASBCA No. 43114, 92-1 BCA ? 24707.

[24]General Engineering & Machine Works, ASBCA No. 38788, 92-3 BCA ? 25055.

[25]Rehabilitation Services of Northern California, ASBCA No. 47085, 96-2 BCA ? 28324.

[26]Labat-Anderson, Inc. v. U.S., 42 Fed.Cl. 806, 857 (1999).

[27]John Reiner & Co. v. United States, 163 Ct.Cl. 381, 325 F.2d 438, 442 (1963).

[28]Krygoski Const. Co., Inc. v. United States, 94 F.3d 1537, 1541 (Fed. Cir. 1996).

[29]Id.

[30]T & M Distributors, Inc. v. United States, 185 F.3d 1279 (Fed. Cir. 1999).

同类推荐
  • Dombey and Son(IV)董贝父子(英文版 下册)

    Dombey and Son(IV)董贝父子(英文版 下册)

    Dombey and Son by Charles Dickens, published in 1848. "Dickens started writing the book in Lausanne, Switzerland, before returning to England, via Paris, to complete it. The story follows a powerful man's callous neglect of his family triggers his professional and personal downfall, showcases the author's gift for vivid characterization and unfailingly realistic description. As Jonathan Lethem contends in his Introduction, Dickens's "genius … is at one with the genius of the form of the novel itself: Dickens willed into existence the most capacious and elastic and versatile kind of novel that could be, one big enough for his vast sentimental yearnings and for every impulse and fear and hesitation in him that countervailed those yearnings too. Never parsimonious and frequently contradictory, he always gives us everything he can, everything he's planned to give, and then more."
  • 离开过 (瑞丽·佩吉悬疑系列 - 第一部)

    离开过 (瑞丽·佩吉悬疑系列 - 第一部)

    在弗吉尼亚州的郊区,一个又一个的女人接连失踪,尸体以恐怖的方式抛弃在荒郊野外,联邦调查局介入破案却一无所获。一个逍遥法外的连环杀人犯。一个陷入危机的城市。重重困难之下,只有一位探员,能够胜任这起艰巨的任务。她就是特别探员瑞丽·佩吉。瑞丽由于不久前刚破获了一起惨无人道的杀人案,正在休假调整。而调查局的人也不愿打扰他们最为出色的探员之一。瑞丽为了不让更多的女人受到伤害,也为了与自己的心魔抗争,坚持重返战场。 为了获得更多线索,瑞丽将深入诡异的玩偶收集者文化圈、伤心的受害者家里、以及杀手内心最黑暗的沟渠。可随着案情的深入,她发现这个杀手的变态程度远远超过任何人的想象。种种原因之下,瑞丽失去了工作,家人安危也受到了威胁,甚至濒临神经崩溃。这是一场争分夺秒的战斗,而瑞丽被逼迫到了绝望的边缘。但是瑞丽·佩吉一旦出马,就决不会退缩。 螳螂捕蝉,黄雀在后。案件无时不刻纠缠着她,带领她探索着人心最黑暗的角落。一系列意想不到的转折之后,瑞丽敏锐的直觉带领着她揭开了案件背后令人震惊的黑幕。《离开过》这本黑暗的心理悬疑小说,标志着这部扣人心弦的恐怖系列的开始。而我们敬爱的主人公瑞丽,将令您废寝忘食,欲罢不能。瑞丽·佩吉系列之第二部即将发行。
  • The Children's Hospital
  • A Tale of Two Cities(双城记)(II)(英文版)

    A Tale of Two Cities(双城记)(II)(英文版)

    It was the time of the French Revolution — a time of great change and great pgsk.comy imprisoned for 18 years in the Bastille, Dr. Alexandre Manette is reunited with his daughter, Lucie, and safely transported from France to England. It would seem that they could take up the threads of their lives in peace. As fate would have it though, the pair are summoned to the Old Bailey to testify against a young Frenchman — Charles Darnay — falsely accused of treason. Strangely enough, Darnay bears an uncanny resemblance to another man in the courtroom, the dissolute lawyer's clerk Sydney Carton. It is a coincidence that saves Darnay from certain doom more than once. Brilliantly plotted, the novel is rich in drama, romance, and heroics that culminate in a daring prison escape in the shadow of the guillotine.
  • The Chronicles of Faerie

    The Chronicles of Faerie

    The third book in this critically acclaimed trilogy, which Booklist described as "shimmering with magic, myth, and romance" Dana has few memories of her mother, who disappeared when she was small. But she has always dreamed, despite her father's discouragement, that her mother would come back one day. When her dad decides to leave Ireland and take a job across the ocean in Canada, Dana is heartbroken. How can she leave her home and the only chance of seeing her mother again? She runs away, high into the fairy mountains of Ireland. Following ancient paths, with a mysterious wolf companion at her side, Dana encounters a world of tragic enchantment and fairy romance, and discovers a great secret about herself. With lush descriptions and rich Celtic lore, plus cameo appearances by characters from the previous books, this latest chronicle will satisfy fans of the series and entice new readers.
热门推荐
  • 茶归暖风时

    茶归暖风时

    “无论如何我都不可能娶那个你们随随便便给我安排的女孩!”五年后“那个……卿卿结个婚?”“不好意思,我不嫁。”女孩撇了他一眼,当初谁把我耍的团团转来着?嫁给他,不可能!男孩沉思了一下,斟酌的开口,“我嫁也行,卿卿你娶我吧!”茶思卿:????【男女主身心干净,1V1,请安心入坑,小甜饼!】
  • 超凡尊者

    超凡尊者

    这是人类新的纪元,是科技正盛的时代,但与其这么说,不如说这是强者的时代…因为不管是地球还是天外天,唯有强者才是真真的主宰
  • 德鲁赛的骑士

    德鲁赛的骑士

    百年德鲁赛风雨飘摇,休布斯帝国百兽环伺,安德烈联邦传奇杰作震撼世间,斯坦勒商盟野心开始膨胀,悲鸣山谷雪怪倾巢南下。时逢乱世,悲歌与战火共存;时逢乱世,求生存上升到为家国;时逢乱世,信仰成为最后的方舟。市井的流浪小儿意外卷入帝国的纷争,他又是否能在这乱世之中存活下来?“一个真正强大的国家,是不需要靠宗教来支撑。”“无边的黑暗之外,将是更广阔的天地。”“笼中的鸟儿,于绝望中度过最美的年华,一个决定,换来新笋的发芽,他的怒火,将掀翻整个帝国。”
  • 火星救援

    火星救援

    六天前,宇航员马克·沃特尼成为了第一批行走在火星上的人。如今,他也将成为第一个葬身火星的人。一场突如其来的沙暴让阿瑞斯3船员被迫放弃任务。撤离过程中,沃特尼遭遇意外,被孤身一人丢在了这片寸草不生的红色荒漠中,剩余的补给也远不够撑到救援可能抵达的那一天。不过,他也许还没机会饿死在这颗星球上。机器故障、环境灾难、人为失误,凡此种种,都有可能抢在饿死之前要他的命。当然,沃特尼也不准备坐以待毙,凭借着他的植物学家和机械工程师背景,他决定跟火星来一场不是你死就是我活的过家家游戏。
  • 封神当大哥

    封神当大哥

    他穿越到了洪荒母亲叫瑶姬,弟弟叫杨戬并且识海中还连接着另一个世界吞噬星空就在他准备依靠这个金手指混的风生水起之时后来的事情一直在刺激他的神经我不是瑶姬的亲儿子,我还有个外公自己爹妈在一块是阴谋?申公豹天生便属大商洪荒种种,经历才知真相附注境界对比洪荒:地仙,天仙,玄仙,上仙,真仙(太乙真仙),金仙,大罗金仙,准圣,圣人吞噬:行星级,恒星级,宇宙级,域主级,界主级(法则承认),不朽,宇宙尊者,宇宙之主,宇宙最强者
  • 天地之灭天

    天地之灭天

    洪荒过后,天下三分。亿万年后,修道界再起波澜,万族纷纷显现,无数强者应时而生。无数人为了追寻传说中的境界——天帝,纷战不休,尸横遍野,血流成河。能否有人登上亘古以来最强的宝座?一个在命运中苦苦挣扎,一个天地不容的人,他到底该何去何从?“命若天定,我便破了这个天。”冷石仰天咆哮……
  • 为蘑菇云升起而奋斗的钱三强

    为蘑菇云升起而奋斗的钱三强

    本书介绍了钱三强的生平,内容包括:更名立志、投师居里夫人、目击地球村的核裂变、25个字的求爱信、启明星故乡的星、世上只有母亲好等。
  • 江山风雨情之雍正与年妃

    江山风雨情之雍正与年妃

    他,爱新觉罗•胤禛,历经九龙夺嫡,最终君临天下;她,名门闺秀,才貌双全。原本天作之合,佳偶一对,却阴差阳错,与爱擦肩。一个错付真心,一个心字成灰,一步错,步步过,错过今生,错过来世,何时才能真心真意爱一回?姐妹情深,兄妹情深,侯门一入深似海,爱恨情仇无止休。天赐良缘,天作之合,千里姻缘一线牵,鸳鸯误点为哪般。爱新觉罗•胤禛、年冰凝;爱新觉罗•胤祯,年玉盈,两兄弟、两姐妹,阴差阳错遇见你,生生世世不分离。本文讲述雍正皇帝与年妃的爱情故事,基本尊重历史,不宫斗,不滥情,不虐恋,数字军团靠边站,康熙也只打打酱油,偶尔搞笑,基本煸情,志矢不渝、无怨无悔,只为写出我心目中的四爷,写出我心目中的爱情。
  • 爹地来了妈咪快跑呀

    爹地来了妈咪快跑呀

    小明星袁默默为了要回股份,闪婚了一个神秘的千亿大boss,一不小心被宠的无法无天!失恋的她,怎么算都觉得赚到了。高颜值、高智商、高收入的总裁老公怎么看都觉得顺眼,唯一的‘缺点’就是太宠太宠太宠她!“老公,外界传言你是高冷男神。”“装的。”“老公,外界传言你是禁欲男神。”“假的。”“老公,外界传言你是Gay。”男人微微抬眸,邪魅一笑,把她壁咚到墙上开口:“外面的传言不靠谱!”宠文、宠文、宠文!推荐漫漫完结文《闪婚娇嫩妻:小叔蜜蜜爱》,VIP书友群:618895719,普通交流群:479994577浏览器粉丝群:390011173
  • 上海滩捕房

    上海滩捕房

    一九二四年九月十五日上午,花旗烟草公司总公司的总裁陆锡侯正在办公,一个职员走进屋,送来一叠信件同往日一样,陆锡侯一封一封地仔细查阅,有封信的信封十分褶皱、肮脏,引起了他的注意。公司的来往公文一向都是十分整洁的,这封怎么会如此肮脏?他抽出来特意查阅,打开一读,不禁一惊,这封信是花旗烟草公司杭州分公司经理孙玉振写来的,内容是说,他于昨天出离公司办事,归来途中被两名匪人绑架,匪人要求公司出资五千元,于明天晚上七时将钱送到湖北路邮电局门前,交给取款人以赎身,如果招来侦探,孙玉振的性命难保。